Bedford-Olney-Northampton
trackbed inspection using Google Earth as to scope of overcoming blockages and
deviation spaces 14-03-2018
Preamble: The desire to record at this stage what blockages of
significance there are and use as a basis for potential interests wishing to
reopen for whatever reason and support these in studies and going forward to
overcome blockages and make reopening happen.
a.
Slow tracks take
a single bi-directional flyover onto and fanning out into a twin track railway
spec for substantial lengths as space and opportunity allow. Key issue north of
River Great Ouse, is there space for a flyover between MML slows and A6 Bypass?
b.
MML – Stevington
Road – reclaim ploughed fields. Bromham/Oakley and Stevington Roads need
bridging.
c.
Relay over
Stevington Walk which occupies trackbed with walk and cycle route slewed
alongside and maybe this per-functory of leisure off road could go as far as
Northampton with deviations where rail priority in engineering or operational
terms must take a priority.
d.
New bridge over
Stevington Road and relay to Turvey not withstanding any blockage on private
land.
e.
Reclaim Turvey
Station area and realign going west to avoid new housing close to the railway
with a sound barrier. Relay track to Clifton Reynes/near as.
f.
New deviation
greater or lesser needed going north of old alignment to cross the Great Ouse
with deep piling around across Lavendon Road and A509 to north or south of
Sewage Works and associated fields between it and River to swing via a new
bridge over Yardley Road to re-join former railway course. Could a new park and
ride station be located west of Yardley Road? Calls for a new A509 Olney road
bypass would slice the railway trajectory in half, so a bridge over or under
the railway and Over Head Line Clearances would be required.
g.
Reclaim trackbed
or slew from Yardley Road to Castle Ashby Estate. Open country to Denton Road
and a new deviation is required to avoid Piddington Station site.
h.
New road bridge
over Denton Road and Brafield Road and a deviation slightly to the south of
Northampton International Raceway Brafield Motor Sports.
i.
Renew bridges
through Great Houghton which lends itself to a halt, ditto Brackmills
Industrial Estate and University of Northampton Riverside Campus.
j.
New access over
or under railway between Salthouse and A428
k.
New access over
or under London Road, must duck to go under Towcester Road Bridge and new
crossing over Bury Port Road or under or bridge the railway.
l.
Rebuild the
railway between Pomfret Close and St Leonards Court to Castle Station.
m. Reconfigure Northampton southern approach tracks to
enable cross over into Platforms 1, 2 and 3 from Brackmills and London
directions and merger.
n.
Could a platform
4 be installed west of Platform 3? This would enable more operational
flexibility. Maybe another under pass under the A4500 road bridge could be inserted
to enable more tracks?
Conclusion: The problems are not insurmountable and as with Olney
we face as per any other reopening or rebuilding or new build railway or road
way, the choice of compulsory purchase and demolition/relocation or avoidance
by modest deviations. The greatest (Olney) is about 1 mile east to west arcing,
the least is utilising what is still open countryside. The aggregate benefits
of the railway lend itself to leisure, recreation as well as a handy public
transport choice and mode which speeds end to end commute timings attracting
more users to choose public transport than the lowest common denominator if you
can’t afford a car and have to take what is on offer of a 1.5-hour durational
end to end journey of just 21.5 miles. It is hoped future studies will bear
these pointers in mind and look at solutions wanting the railway reopened than
problems to oppose the railway not facing the default consequences of
congestion, queues, parking access issues and costs spiralling which affects everyone.
__Fill In, Tear Off and Send with Your
Subscription. Please help us recruit more members! __
ERTA,
come to our local Forums and offer time and talent as you may?
Tick
if a New Member: o_____
Tick
if renewing as an existing member: o_____
Name: __________________________
Address: __________________________________________________
Postcode: _______________ Tel/Mobile: __________________
Membership is £10 per
year*
*All
members are responsible for ensuring the association can function properly.
There
are voluntary jobs to do such as keeping records, raising funds, recruiting new
people and ensuring the association achieves more of its aims. It is voluntary.
Signed:
___________________________ Dated: ____________________
Please send completed
form to ERTA Membership: Mr Richard Pill, ERTA, 24c St Michael’s Road, Bedford,
MK40 2LT or see https://ertarail.com/membership/
No comments: